The world’s largest oil-fired power plant unit 2 completes synchronization successfully

2019-3-15 16:15:08

At 8:00 a.m. of March 13th, 2019, Saudi Yanbu Phase III Project Unit 2 completed synchronization successfully at the first time. The steam turbines, generators, main transformers, plant transformers and other equipments are operated smoothly with excellent parameters & various systems, and gets highly praise from owner, supervisor and other related parties.

Saudi Yanbu Phase III 5×660MW Oil-fired Project is the world’s largest oil-fired project and is also the important livelihood & political project. This project gets the highly attention from Saudi government and social sectors, and Saudi minister has been visited the site for 3 times. It has the vital strategy significance for SEPCOIII improving brand image.

The project EPC contract was signed on May 7th, 2017 and the construction work was started on May 17th, 2017. During the construction period, SEPCOIII uses the international quality & safety management system and strong EPC chain to guarantee the project efficiency progress. Meanwhile, this project provides more than 13,000 work opportunities for more than 10 countries that along The Belt and Road, and also helps Saudi government to achieve Saudi Vision 2030.



上海福彩开奖结果 任选一怎么算中奖 分分彩不亏钱的玩法 奔驰宝马下载 欢乐生肖开奖历史走势图 大乐透走势图100期 捕鱼来了辅助一炮死 孙悟空齐天大圣游戏 牌九至尊手机版 安徽时时遗漏 天天捕鱼破解版 赛车北京pk10记录 浙江11选5计划软件 手机上玩牛牛是骗局吗 刺激战场主播游戏名 拉钢筋平板车赚钱吗 作家赚钱多难