Bangladesh Sirajganj S4 Project completes 168 hours reliable operation successfully

2019-4-9 15:56:31

At 18:00 am of Apr 8, Bangladesh Sirajaganj S4 Project completed 168 hours reliable operation successfully and completed the COD 11 days ahead of contract time.

Bangladesh Sirajganj S4 414MW Project is the earliest start construction energy project in Bangladesh, and has the important influence for joining the Belt and Road Initiative and deepening the cooperation between China &Bangladesh. During the project construction period, this project has been provided more than 3000 work opportunities for local people and improve their income level. After the project construction, it will generate electricity to Dacca for benefiting people.   